Short answer: what should BESS teams agree before selecting a pre-charge circuit?
Before specifying a custom ESS PDU or high-voltage junction box, agree where pre-charge takes place, which controller owns the sequence, how completion is measured, and what happens if the sequence fails. Confirm these interfaces with both the battery and PCS suppliers.
Pre-charge limits the inrush associated with charging a DC-link capacitor before the main power connection is completed. Texas Instruments explains this principle in its high-voltage passive pre-charge reference design, which lists battery energy storage among its applications.[1] The reference design is background material; its component values and timing are not requirements for a particular BESS.
The interface template below is a proposed framework for project discussion. It does not prescribe a universal BMS, PCS or EMS control architecture.
1. Establish the actual electrical boundary
A system overview may show battery racks, an ESS PDU/HVJB and a PCS. That overview alone does not identify every switching device or energized bus section. A rack may have its own disconnects, the PCS may include a pre-charge function, and multiple racks may share a DC bus.
Start with a single-line diagram that identifies:
Ask whether pre-charge is intended to charge the PCS DC link, another bus section, or both. For a common bus, define how connecting an additional rack differs from starting an initially discharged system. Rack-to-bus voltage matching and connection permission need a separate review; a successful initial bus pre-charge does not settle every later rack connection.
- Battery-side switching and rack connection points.
- Each ESS PDU/HVJB input and output branch.
- The PCS DC input, its DC-link capacitance and any internal pre-charge circuit.
- Voltage measurement locations on both sides of the intended connection.
- Discharge paths and possible alternative sources of bus voltage.
2. Separate circuit location from control ownership
The enclosure containing the pre-charge branch does not automatically own the startup logic. A circuit inside an ESS PDU may receive commands from another controller. A PCS with internal pre-charge may still require battery-side permission and switching coordination.
Record four distinct responsibilities:
An EMS start request should be distinguished from permission to energize a particular DC branch. Assign that permission explicitly, including local protection vetoes and command priority. Avoid two controllers independently commanding the same switch without defined arbitration.
- Hardware provider: supplies and documents the pre-charge circuit and associated switching devices.
- Sequence owner: evaluates prerequisites and controls the authorized startup sequence.
- Measurement provider: supplies the voltage, current or device-status information used by that sequence.
- Acceptance owner: approves the integrated behavior and evidence before system release.
3. BMS/PCS pre-charge interface matrix
Use this matrix to prepare an interface control document. The candidate participants are discussion inputs, not assigned responsibilities. Name the actual device and responsible organization for each row before design release.
Keep command, acknowledgement, measured status and derived permission as separate interface items. A command to close a contactor is not proof that its contacts closed. Auxiliary feedback and voltage plausibility can support diagnostics, but their diagnostic coverage must be assessed for the selected hardware and topology.
| Decision / interface | Typical participants | Required evidence |
|---|---|---|
| Startup request | EMS, plant controller or designated system controller | Request source, cancellation, priority and relationship to local permission Evidence: Approved request and permission logic |
| Battery connection permission | Rack BMS, master BMS and system controller | Required battery states, inhibit conditions and validity period Evidence: Permission/inhibit signal map |
| PCS readiness | PCS and sequence owner | DC input readiness, internal pre-charge status and power-conversion inhibit Evidence: PCS startup interface specification |
| Voltage measurements | Battery electronics, PDU sensing and/or PCS | Measurement nodes, polarity, accuracy, update period, timestamps and invalid-data behavior Evidence: Measurement map and tolerances |
| Pre-charge command | Designated sequence owner and circuit controller | Command recipient, acknowledgement, timeout and abort behavior Evidence: Command/status definition |
| Completion decision | Sequence owner using validated measurements | Permitted voltage difference, stability interval, current criterion if used and maximum duration Evidence: Documented completion criteria |
| Main switching | Designated controller and switch hardware | Closing permission, actual-position feedback where available and command arbitration Evidence: Approved switching sequence |
| Pre-charge branch release | Sequence owner and branch controller | Transition conditions, feedback and handling of failure to disengage Evidence: Transition and abnormal-state tests |
| Fault handling | Local protection, BMS, PCS and system controller | Detection owner, affected branch, conversion stop request and switching action Evidence: Fault-response table |
| Reset and retry | Sequence owner, protection controller and service interface | Retry permission, thermal recovery, attempt limit and manual-reset conditions Evidence: Approved restart policy |
| Communication or auxiliary-power loss | Each affected controller and hardware supplier | Stale-data detection, device behavior and recovery prerequisites Evidence: Loss-of-signal and power-loss tests |
| Shutdown and discharge | PCS, discharge hardware and system controller | Stored-energy boundary, discharge responsibility and voltage confirmation Evidence: Shutdown/discharge acceptance record |
4. Define completion as a measurable condition
“Pre-charge complete” needs an agreed technical meaning. Document the voltage difference allowed across the connection being closed, the validity of the measurements, the maximum allowed duration and any required stability interval. Include current behavior where it forms part of the design.
Do not copy a fixed percentage or time from another platform. Switching requirements, capacitance, initial bus voltage, measurement error and connected loads can change the decision. A timeout should identify an unsuccessful attempt; elapsed time alone should not be assumed to prove the bus is ready.
For passive resistor pre-charge, TI highlights system voltage, capacitance, charge duration and resistor pulse-energy capability as design inputs.[1] Continuous resistor wattage alone is not a sufficient specification. Repeated attempts also require a thermal and recovery review.
5. Obtain these inputs from the PCS and battery teams
Request the effective capacitance seen at the connection under review, including relevant tolerance and operating configuration. Confirm whether the PCS provides internal pre-charge, whether it can draw DC current during startup, and what happens when its AC side is energized.
The battery team should provide the operating voltage range, rack connection arrangement, available switching functions and connection-permission logic. For parallel racks, clarify the conditions for adding or reconnecting a rack to an energized bus.
The interface package should also identify:
A system voltage and power rating are useful starting points, but they do not define the pre-charge interface by themselves.
- Maximum initial voltage difference and possible residual DC-link voltage.
- Expected startup and restart frequency, including interrupted attempts.
- Switching-device closing and interruption constraints from the selected supplier.
- Available sensing, auxiliary contacts, communication interfaces and auxiliary power.
- Installation temperature, mounting, cooling and enclosure constraints.
- Discharge ownership and confirmation of residual voltage before the next state.
6. Agree abnormal behavior before the prototype build
Build a fault-response table alongside the normal startup sequence. For each event, record who detects it, which permissions are withdrawn, what hardware can interrupt the actual current, what is logged and what permits recovery.
Review at least failure to reach the completion condition, invalid voltage data, unexpected bus voltage, contactor feedback mismatch, communication loss, auxiliary-power loss and excessive repeat attempts.
Distinguish a controlled stop from emergency fault interruption. Do not assume every contactor can interrupt every prospective fault current. The switching and protective-device responsibilities must follow the approved system protection design and component ratings.
Record whether a fault latches, whether another attempt is permitted and how stored energy is handled. An automatic retry should be an approved design behavior with defined limits.
7. Validation scope for the integrated system
Plan validation around the agreed interfaces and operating limits. The review should cover normal startup, relevant voltage extremes, capacitance variation, residual bus voltage, temperature and permitted repeat-start conditions. Include interrupted startup and injected interface faults where appropriate to the validation plan.
For each test, retain the hardware configuration, firmware revision, initial conditions, measurement locations, commands, actual feedback, waveforms, acceptance criteria and result. A single successful startup does not validate every supported configuration.
Separate component evidence, PDU assembly checks and integrated BESS validation. State which organization performs and accepts each part; do not describe planned tests as completed tests.
8. OEM RFQ checklist for a custom ESS PDU/HVJB
Mark unavailable inputs as open items with a responsible party and target decision date. This makes the limits of an early quotation visible and helps avoid treating an initial concept as a released design.
| Decision / interface | Typical participants | Required evidence |
|---|---|---|
| Application and topology | OEM / engineering team | BESS type, rack count, PCS arrangement and system single-line diagram |
| Electrical operating range | OEM / engineering team | Minimum/nominal/maximum DC voltage; continuous and peak current with duration |
| Pre-charge boundary | OEM / engineering team | Bus section to be charged, hardware location and internal PCS functions |
| PCS data | OEM / engineering team | Effective input capacitance, initial-voltage conditions and startup requirements |
| Switching and protection | OEM / engineering team | Device locations, responsibility boundaries and available fault-current information |
| Control interfaces | OEM / engineering team | Sequence owner, signal list, communication protocol and message definitions |
| Completion and recovery | OEM / engineering team | Closing criteria, timeout, fault response, retry and reset policy |
| Mechanical interfaces | OEM / engineering team | Envelope, mounting, connectors, cable directions and enclosure requirements |
| Validation | OEM / engineering team | Applicable project requirements, test ownership, acceptance criteria and records |
| Commercial scope | OEM / engineering team | Prototype quantity, estimated production volume and target schedule |

Technical references
- TI TIDA-050080 / TIDUF73
Background on pre-charge principle and passive circuit design, not a prescribed BESS control architecture.
References explain general concepts, not verified TRHT ratings or certification. Required product evidence remains configuration-specific.
Frequently asked questions
Does every ESS PDU need an internal pre-charge circuit?+
No. Circuit location and scope depend on the system architecture and existing battery/PCS functions. Confirm the electrical boundary before adding a branch.
Should the BMS or PCS control pre-charge?+
The project should designate one sequence owner and define the permissions and feedback supplied by the other devices. There is no universal assignment for every BESS architecture.
Can the same timing be used for every PCS?+
It should not be assumed. Confirm capacitance, startup behavior, voltage conditions, switching requirements and the selected circuit before accepting timing.
Is pre-charge completion sufficient permission to start power conversion?+
No. The PCS and system controller must also satisfy the other startup permissions defined for the project. Keep bus preparation and conversion enable as distinct states.
What should we send TRHT for an initial review?+
Send your system diagram, voltage/current range, PCS DC-input information, control interface requirements and mechanical constraints. Identify any unresolved responsibility boundaries so they can be included in the review.